Inspection & Installation

Inspection:

There are five parts need to be inspected.

1.Inspection of material:we will send each batch of steel plate to laboratory to check whether the material is high quality.We are sure all the raw materials we use is good.

2.Inspection of length:we will Maintain normal error is within 2 mm.

3.Inspection of thickness:We will maintain normal error is within 1 mm.

4.Inspection of pitch-row: Keep the error in one millimeter of plus or minus.

5.Inspection of Jonit:The height of joint>=the thinnest plate thickness*0.7.

baofen 750 模板

 

Installation:

The Installation of steel structure building process can be divided into five parts:

1.make foundation
(1)making the anchor cage according to the drawings. IMG_5402
(2)making the foundation according to foundation drawing IMG_5402



2.install the main structure
(1)install the steel columns according to the layout chart. IMG_5402
(2)do the whole assembly of steel beam according to the installation structure layout IMG_5402 installation6


3. install purlin , knee brace, brace and pole
(1)install the purlin according to the roof purlin layout.(2)install the knee braces according to the roof structural layout the connecting node of knee brace.(3)install the brace and pole according to the roof structural layout.(4)install the wall bracing according to the preceding purlin arrangement. IMG_5402

 



4. install roof, wall panels and accessories
(1)install the roof panel(2) install the ridge tile(3) install the wall panels(4)Install the cornice accessories IMG_5402
5.install doors and windows
(1)install windows IMG_5402
(2)install the roll-up door IMG_5402

 

This the installation of the whole building is completed , the overall appearance is as the following diagram IMG_5402